Installation requirements for double helix cone mixer
1. The double-spiral conical mixer is mounted on a tight, horizontal, vibration-free platform with appropriate distances around it for discharge. The distance from the discharge port to the ground can be selected according to the process flow.
2. Before using the equipment, the foreign objects in the equipment should be cleaned, and the rotating parts should be lubricated to ensure that the gear box does not leak oil to avoid contaminating the mixed medium.
3. Observe the spiral steering after turning on the power. Make sure that the double helix (looking down from the feed port) rotates clockwise. When the screw rotates clockwise, the material can be mixed smoothly, otherwise the screw will be broken or even the gear box will be destroyed. (Must be operated in strict accordance with the operating regulations).
4. Test run before starting the machine, first turn on the oil pump and then turn on the rotating motor. After the screw rotation direction is correct, try running for 20-30 minutes before feeding.
5. Note that you must first turn on the machine and then feed it to avoid damage to the screw.
6. Regularly add lubricant to the gearbox. The oil level is appropriate at the center of the oil mark. 40# or 50# oil is used for normal temperature. It is recommended to use 70# or 90# machine pressure industrial gear oil to improve the service life of the equipment.
7. When the reducer is greased, it is recommended to use special grease 2L molybdenum disulfide or 2L2# lithium grease. Grease should be installed in the reducer 1/3~1/2. 8. The gearbox drive head is greased and greased before delivery. Replace the worn iron scraps after 300 hours of use to improve the service life of the equipment. Replace it 3 months after normal use (10h every working day), and replace the lubricant for 6 months after intermittent work.